Project Decritption

General Contractor – Unico Hotel Jamaica 451 Rooms Hotel

Scope

4 Towers of 12 floor height, with Post-tense System and 45,000 m2 of general areas cocrete frame structures, along with all the exterior works and ancillary buildings. Convention Center made of Large
Metal Structure

Activities

  • General project Execution and Coordination.
  • Earthworks of the 170,000 M2 land (including excavation and backfill)
  • Foundation Works (Pilecaps, Foundation slabs and isolated footings)
  • Block Walls and Concrete stiffener columns & beams.
  • Pre-fabricated Showers.
  • Marble & Porcelain Flooring and wall tiling.
  • Facades Panels Novidesa & Alucobond system
  • Tripple height slabs at the lobby areas , made of concrete.
  • Manage Machinery and equipments (tower cranes, elevators, etc)
  • .

Project Information

Client:

Unico Hotels

Location:

LOCATION: MONTEGO BAY , ST. JAMES// JAMAICA

Date:

2022-Current