Project Description
Exterior Civil Works after earth works (road kerbs / Asphalt works / walkways / catch basin for storm water drains / Road Signage / Ladscape Coordination & Washed Concrete Walkways / Concrete Pavers (adoquines).
Scope
All Exterior activities In the hotel after completion of all earthworks, from earthworks up to final completion of all the Hotel amenities.
Activities
- Asphalt Roads with signage
- Concrete Kerbs cast in place
- Concrete walkways broom finished
- Washed Concrete
- Coordination for Landscape Coordination
- Concrete Paversf (adoquinado) laid.
Project Information
Client:
Princess Hotel
Location:
GREEN ISLAND, HANOVER // JAMAICA
Date:
2023-2024